Risk Assessment
| 
Date  | 
Hazard | 
Level of Risk  
(Low, Medium, High  | 
Prevention | 
Issues | 
| 
20/2/2014 | 
Debris at location  | 
Medium | 
Make sure area of the location is empty of debris that
  will cause harm or injury to actors or crew | 
Some of the actors got hurt by some of the nettle bushes
  however we moved away from the bushes   | 
| 
24/02/2014 | 
People interfering with the production  | 
Low  | 
Make sure location and time is right where there are
  hardly any public around so it doesn’t interfere with filming. i.e. cause
  actors to loose contraction.  | 
 There was no issue
  as the locations were the public didn’t go and we got the production done
  early while no one was really awake.   | 
| 
24/02/2014 | 
Weather  | 
Medium  | 
Make sure the weather condition is acceptable for
  production. 
Take umbrella in case of rain so characters clothing
  doesn’t get wet.   | 
The only issue with the weather was that before production
  the weather was heavy rain. It stopped before production got called off and
  thanks to the rain , it created a dull environment which fitted perfectly to
  the scene.  | 